The Altair Community is migrating to a new platform to provide a better experience for you. In preparation for the migration, the Altair Community is on read-only mode from October 28 - November 6, 2024. Technical support via cases will continue to work as is. For any urgent requests from Students/Faculty members, please submit the form linked here

I can’t figure out how to make a cumulative variance chart

NeuronerdNeuronerd Member Posts: 6 Learner III
edited March 2020 in Help
I’m using the PCA operator and I just can’t seem to find anywhere that will let me just simply make a cumulative variance chart. Any ideas?

Answers

  • jmerglerjmergler Employee-RapidMiner, RapidMiner Certified Analyst, Member, University Professor Posts: 41 Guru
    Hi @Neuronerd,
    Does the following work for you? First make sure you capture the  PCA.preprocessing model (pre)

    Then in results, for the PCA model, select the Cumulative Variance tab.
     
  • NeuronerdNeuronerd Member Posts: 6 Learner III
    @jmergler Yes that worked, I forgot to do the pre! Thank you